Development Update

2018
April - Start of construction of Nash Street/Selby Street roundabout
March - Sale of first development sites to Iris Residential and Fini Group - find out more
March - Start of Nash Street/Selby Street intersection upgrade and roundabout construction
February - Start of civil construction works

2017
May - Release of first development sites (Lot 37 and Lot 38)
April to September - Earthworks and removal of hospital buildings

2016
December - Approval of the Shenton Park Hospital Redevelopment Improvement Scheme by the Minister for Planning
February - Community information sessions
January to April - Public comment period for WAPC draft Shenton Park Hospital Redevelopment Improvement Scheme

2015
August and September - Public comment period for WAPC amendment to transfer the Public Purposes (Hospital) reservation to the Urban zone in the Metropolitan Region Scheme.
January - Draft Master Plan public comment period closed

2014
December - Draft Master Plan public comment period opened, including an Infomation Session at Subiaco Community Centre
October - Shenton Park Rehabilitation Hospital closed
August - Online survey seeking community feedback on future redevelopment of the site