May 2017 - Cockburn Central West works are completed and is now open.

May 2017 - Cockburn ARC opens.

May 2016 - Stage 1 civil works completed. Landscaping works expected to be completed at the end of 2016.

November 2015 - Stage 1 lots available for sale

September 2015 - Stage 1 lots Registration of Interest process opens.

July 2015 - Work commences on Stage 1 of Cockburn Central West. Works are expected to completed in April 2016.

July 2015 - Work commences on the Cockburn Recreation and Aquatic Centre and Fremantle Dockers facility. Completion is expected in early 2017.

Mid 2014 - Cockburn Central West forward works to commence

 